Status meeting

Electrical Hardware

This week:
  • Worked on Eagle Layout and started BOM Layout
  • Worked on main board fixes (stepper driver)
  • Sent mechanical requirements for back to mechanical group.
Next week:
  • Finish layout for BOM
  • More work on main board

High Level Software

This week:
  • BOM simulation with orientation!
  • BOM readings service running in simulation
  • No update on LCM
Next week:
  • BOM control class
  • Start writing simple behaviors using BOM simulation
  • get some update on LCM
  • (questions on our charging station setup)

Low Level Software

This week:
  • New BOM sending code finished.
  • I didn't have enough time to work on i2c.
Next week:
  • Test BOM sending/receiving.
  • Write i2c code.

Mechanical Hardware

This week:
  • met and handed out tasks for Solidworks and basic modular design
Next week:
  • received electronic part list, add to modular chassis design
  • Solidworks models for several other parts